Groundworks Pile Up

Groundworks to level the site at Synder Meadow Pavilions were completed and piling began by the end of October. In a few short days they were in and the attenuation tank installed. The beginning of November saw foundation pads and beams dug and the rebar installed. With inspection now complete, the concrete pour can follow.

Pavilion Construction – Work Has Begun!

On week commencing 13 October 2025 Despite the rain, exciting progress is underway! Hinton Design & Build are now officially on site and construction has begun on the new Synder Meadow Pavilion. Initial surveying completeSite stripped and preparedPiling mats installedHaul road stripped and laidAll works overseen and formally signed off by the appointed archaeologist This …